PNRA's regulatory oversight of a nuclear power plant covers:
A. Only construction
B. Only operation
C. Only decommissioning
D. The full lifecycle from site evaluation to decommissioning
Correct Answer: D
PNRA regulates the full lifecycle, including siting, design, construction, commissioning, operation and decommissioning.
CSS - PMS - CCE - PCS - Pakistan Affairs (P.A)
Chashma Nuclear Power Plant
Which body determines electricity tariffs generally in Pakistan, rather than nuclear safety licensing?
A. PNRA
B. NEPRA
C. PAEC
D. IAEA
Correct Answer: B
NEPRA regulates Pakistan's electric power sector, while PNRA is responsible for nuclear safety regulation.
CSS - PMS - CCE - PCS - Pakistan Affairs (P.A)
Chashma Nuclear Power Plant
What is PNRA's primary role regarding Chashma nuclear plants?
A. Generating electricity
B. Fuel mining
C. Nuclear safety regulation and licensing
D. Electricity tariff determination
Correct Answer: C
PNRA regulates nuclear installations through licensing, inspection, review and assessment.
CSS - PMS - CCE - PCS - Pakistan Affairs (P.A)
Chashma Nuclear Power Plant
All four operating Chashma nuclear plants are under safeguards of which international organization?
A. WHO
B. IAEA
C. UNESCO
D. WTO
Correct Answer: B
PAEC states that all four operational Chashma plants are under IAEA safeguards.
CSS - PMS - CCE - PCS - Pakistan Affairs (P.A)
Chashma Nuclear Power Plant
If C-5's 1,200 MWe gross capacity is added to the existing 1,330 MWe at Chashma, the site's gross capacity would become about:
A. 1,530 MWe
B. 2,200 MWe
C. 2,530 MWe
D. 3,530 MWe
Correct Answer: C
1,330 MWe + 1,200 MWe gives approximately 2,530 MWe gross capacity.
CSS - PMS - CCE - PCS - Pakistan Affairs (P.A)
Chashma Nuclear Power Plant
Chashma-5 is expected to enter operation around which year according to current project information?
A. 2027
B. 2028
C. 2030
D. 2035
Correct Answer: C
Current international project information indicates operation around 2030.
CSS - PMS - CCE - PCS - Pakistan Affairs (P.A)
Chashma Nuclear Power Plant
The IAEA Board of Governors approved an item-specific safeguards agreement for C-5 in:
A. 2023
B. 2024
C. 2025
D. 2026
Correct Answer: D
The IAEA Board approved an item-specific safeguards agreement for C-5 in March 2026.
CSS - PMS - CCE - PCS - Pakistan Affairs (P.A)
Chashma Nuclear Power Plant
The announced 2023 deal for Chashma-5 was valued at approximately:
A. US$1.2 billion
B. US$2.5 billion
C. US$4.8 billion
D. US$10 billion
Correct Answer: C
The Chashma-5 deal announced in 2023 was reported at about US$4.8 billion.
CSS - PMS - CCE - PCS - Pakistan Affairs (P.A)
Chashma Nuclear Power Plant
Which organization is the main Chinese nuclear partner associated with Chashma-5?
A. CNNC
B. Rosatom
C. EDF
D. Westinghouse
Correct Answer: A
China National Nuclear Corporation (CNNC) is the key Chinese partner associated with the project.
CSS - PMS - CCE - PCS - Pakistan Affairs (P.A)
Chashma Nuclear Power Plant
First concrete for Chashma-5 was poured in:
A. June 2023
B. December 2024
C. March 2025
D. March 2026
Correct Answer: B
First concrete was poured at the end of December 2024, marking formal construction start.
CSS - PMS - CCE - PCS - Pakistan Affairs (P.A)
Chashma Nuclear Power Plant
When did PNRA issue the construction license for C-5?
A. July 2023
B. April 2024
C. 26 December 2024
D. March 2026
Correct Answer: C
PNRA issued the C-5 construction license on 26 December 2024.
CSS - PMS - CCE - PCS - Pakistan Affairs (P.A)
Chashma Nuclear Power Plant
When was the groundbreaking ceremony for C-5 held?
A. 14 July 2023
B. 26 December 2024
C. 30 December 2024
D. 1 March 2026
Correct Answer: A
The groundbreaking ceremony was held on 14 July 2023.
CSS - PMS - CCE - PCS - Pakistan Affairs (P.A)
Chashma Nuclear Power Plant
Who performed the groundbreaking ceremony for C-5 on 14 July 2023?
A. President of Pakistan
B. Prime Minister Shehbaz Sharif
C. Chairman Senate
D. Governor Punjab
Correct Answer: B
PAEC records that Prime Minister Shehbaz Sharif performed the C-5 groundbreaking ceremony on 14 July 2023.
CSS - PMS - CCE - PCS - Pakistan Affairs (P.A)
Chashma Nuclear Power Plant
Approximately what net capacity is listed for Chashma-5 by the World Nuclear Association?
A. 315 MWe
B. 650 MWe
C. 1,100 MWe
D. 1,330 MWe
Correct Answer: C
The World Nuclear Association lists about 1,100 MWe net capacity for Chashma-5.
CSS - PMS - CCE - PCS - Pakistan Affairs (P.A)
Chashma Nuclear Power Plant
What is the gross generating capacity of C-5 according to PNRA/PAEC?
A. 340 MWe
B. 600 MWe
C. 1,100 MWe
D. 1,200 MWe
Correct Answer: D
C-5 is rated at 1,200 MWe gross capacity by PNRA/PAEC.
CSS - PMS - CCE - PCS - Pakistan Affairs (P.A)
Chashma Nuclear Power Plant
C-5 is designed as how many primary coolant loops according to PNRA?
A. One
B. Two
C. Three
D. Four
Correct Answer: C
PNRA describes C-5 as a three-loop pressurized water reactor.
CSS - PMS - CCE - PCS - Pakistan Affairs (P.A)
Chashma Nuclear Power Plant
C-5 is based on which reactor family/design?
A. CANDU
B. Hualong One / HPR1000
C. RBMK
D. Magnox
Correct Answer: B
C-5 is a Hualong One (HPR1000) pressurized water reactor project.
CSS - PMS - CCE - PCS - Pakistan Affairs (P.A)
Chashma Nuclear Power Plant
What is the status of C-5 as of September 2026?
A. Decommissioned
B. Operational
C. Under construction
D. Cancelled
Correct Answer: C
C-5 is under construction at the Chashma site.
CSS - PMS - CCE - PCS - Pakistan Affairs (P.A)
Chashma Nuclear Power Plant
What is the designation of the fifth nuclear power unit at Chashma?
A. K-5
B. C-5
C. N-5
D. P-5
Correct Answer: B
The fifth unit at Chashma is designated C-5.
CSS - PMS - CCE - PCS - Pakistan Affairs (P.A)
Chashma Nuclear Power Plant
Which two units received operating licenses from PNRA on 2 May 2018?
A. C-1 and C-2
B. C-2 and C-3
C. C-3 and C-4
D. C-4 and C-5
Correct Answer: C
PNRA granted operating licenses to C-3 and C-4 on 2 May 2018.