CSS - PMS - CCE - PCS - Pakistan Affairs (P.A)
Planning Commission
For Planning Commission, which option correctly gives the "PC-II"?
A. Project monitoring and progress reporting
B. Public Sector Development Programme
C. Project completion reporting
D. Feasibility studies and surveys
Correct Answer: D
Pc-ii: Feasibility studies and surveys. PC-II is commonly used to seek approval for feasibility and preparatory studies.
CSS - PMS - CCE - PCS - Pakistan Affairs (P.A)
Planning Commission
For Planning Commission, which option correctly gives the "project appraisal"?
A. Five-Year Plans
B. PC-I
C. Annual Plan
D. Annual Budget Statement
Correct Answer: B
Project appraisal: PC-I. The PC-I form presents project objectives, costs, benefits and implementation arrangements.
CSS - PMS - CCE - PCS - Pakistan Affairs (P.A)
Planning Commission
For Planning Commission, which option correctly gives the "PSDP"?
A. Post-completion evaluation
B. Feasibility studies and surveys
C. Public Sector Development Programme
D. National development planning and coordination
Correct Answer: C
Psdp: Public Sector Development Programme. The PSDP lists federally funded development projects and allocations.
CSS - PMS - CCE - PCS - Pakistan Affairs (P.A)
Planning Commission
For Planning Commission, which option correctly gives the "ministry link"?
A. Executive Committee of the National Economic Council
B. National Economic Council
C. Central Development Working Party
D. Ministry of Planning, Development and Special Initiatives
Correct Answer: D
Ministry link: Ministry of Planning, Development and Special Initiatives. The federal planning ministry provides the institutional home for national development planning.
CSS - PMS - CCE - PCS - Pakistan Affairs (P.A)
Planning Commission
For Planning Commission, which option correctly gives the "role"?
A. Many development sectors are implemented by provinces
B. Feasibility studies and surveys
C. Public Sector Development Programme
D. National development planning and coordination
Correct Answer: D
Role: National development planning and coordination. The Planning Commission prepares development frameworks, appraises projects and coordinates public investment priorities.
CSS - PMS - CCE - PCS - Pakistan Affairs (P.A)
Planning Commission
Why is provincial coordination important to the Planning Commission?
A. Many development sectors are implemented by provinces
B. National development planning and coordination
C. Project completion reporting
D. Public Sector Development Programme
Correct Answer: A
Federal planning must align infrastructure, social-sector and regional priorities with provincial responsibilities.
CSS - PMS - CCE - PCS - Pakistan Affairs (P.A)
Planning Commission
What type of planning document sets longer-term goals beyond annual budgets?
A. National development planning and coordination
B. National vision or development framework
C. Post-completion evaluation
D. Project completion reporting
Correct Answer: B
Long-term vision documents guide structural priorities across governments.
CSS - PMS - CCE - PCS - Pakistan Affairs (P.A)
Planning Commission
What shorter planning document translates medium-term priorities into yearly targets?
A. Five-Year Plans
B. Annual Plan
C. National Finance Commission Award
D. PC-I
Correct Answer: B
Annual Plans set yearly development targets and resource allocations.
CSS - PMS - CCE - PCS - Pakistan Affairs (P.A)
Planning Commission
Which planning instrument historically organized medium-term national development priorities?
A. Annual Plan
B. Five-Year Plans
C. PC-I
D. Annual Budget Statement
Correct Answer: B
Pakistan used successive Five-Year Plans for development strategy.
CSS - PMS - CCE - PCS - Pakistan Affairs (P.A)
Planning Commission
Which constitutional body sets broad national economic and development policy?
A. Ministry of Planning, Development and Special Initiatives
B. Central Development Working Party
C. Executive Committee of the National Economic Council
D. National Economic Council
Correct Answer: D
The NEC brings together federal and provincial leadership for national economic planning.
CSS - PMS - CCE - PCS - Pakistan Affairs (P.A)
Planning Commission
What does CDWP stand for?
A. Executive Committee of the National Economic Council
B. Central Development Working Party
C. Ministry of Planning, Development and Special Initiatives
D. National Economic Council
Correct Answer: B
CDWP reviews and approves projects within delegated limits and recommends larger ones to ECNEC.
CSS - PMS - CCE - PCS - Pakistan Affairs (P.A)
Planning Commission
Which high-level body approves very large public-sector projects and policies?
A. National Economic Council
B. Ministry of Planning, Development and Special Initiatives
C. Central Development Working Party
D. Executive Committee of the National Economic Council
Correct Answer: D
ECNEC approves major development projects and economic matters.
CSS - PMS - CCE - PCS - Pakistan Affairs (P.A)
Planning Commission
What does PC-V primarily concern?
A. Public Sector Development Programme
B. Post-completion evaluation
C. Project completion reporting
D. Feasibility studies and surveys
Correct Answer: B
PC-V is used to assess project performance after completion.
CSS - PMS - CCE - PCS - Pakistan Affairs (P.A)
Planning Commission
What is PC-IV generally used for?
A. Project completion reporting
B. Project monitoring and progress reporting
C. National development planning and coordination
D. National vision or development framework
Correct Answer: A
PC-IV records completion and final project status.
CSS - PMS - CCE - PCS - Pakistan Affairs (P.A)
Planning Commission
What is the PC-III form mainly associated with?
A. Project monitoring and progress reporting
B. Many development sectors are implemented by provinces
C. Post-completion evaluation
D. National development planning and coordination
Correct Answer: A
PC-III supports monitoring of ongoing development projects.
CSS - PMS - CCE - PCS - Pakistan Affairs (P.A)
Planning Commission
What is the PC-II form generally used for?
A. Post-completion evaluation
B. Project completion reporting
C. Many development sectors are implemented by provinces
D. Feasibility studies and surveys
Correct Answer: D
PC-II is commonly used to seek approval for feasibility and preparatory studies.
CSS - PMS - CCE - PCS - Pakistan Affairs (P.A)
Planning Commission
Which document is commonly used to propose a major public-sector development project?
A. Five-Year Plans
B. Annual Plan
C. PC-I
D. Annual Budget Statement
Correct Answer: C
The PC-I form presents project objectives, costs, benefits and implementation arrangements.
CSS - PMS - CCE - PCS - Pakistan Affairs (P.A)
Planning Commission
What does PSDP stand for?
A. Public Sector Development Programme
B. Post-completion evaluation
C. Feasibility studies and surveys
D. Project monitoring and progress reporting
Correct Answer: A
The PSDP lists federally funded development projects and allocations.
CSS - PMS - CCE - PCS - Pakistan Affairs (P.A)
Planning Commission
The Planning Commission works under which federal portfolio?
A. National Economic Council
B. Central Development Working Party
C. Ministry of Planning, Development and Special Initiatives
D. Executive Committee of the National Economic Council
Correct Answer: C
The federal planning ministry provides the institutional home for national development planning.
CSS - PMS - CCE - PCS - Pakistan Affairs (P.A)
Planning Commission
What is the central role of Pakistan's Planning Commission?
A. National development planning and coordination
B. Post-completion evaluation
C. Feasibility studies and surveys
D. Public Sector Development Programme
Correct Answer: A
The Planning Commission prepares development frameworks, appraises projects and coordinates public investment priorities.